A private party or parties who construct any sewer line five hundred feet or more in length which will be of use to and benefit properties of others shall be entitled to reimbursement of a portion of the actual costs of the construction when the following requirements have been met:

A. Prior to construction of the sewer line, the Board agrees to repayment for the reimbursable portion of the work;

B. The construction of the line is completed in accordance with plans and specifications approved by the District Engineer and is inspected and accepted by the District Engineer;

C. The party claiming reimbursement provides satisfactory evidence to show the actual cost of construction, including engineering costs. (Ord. 72 §1, 1991; Ord. 54 §1, 1986; Ord. 3 §7.2, 1973)